| PROPOSED DATES |
ACTIONS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cleaning |
|
|
Painting- Master & Office |
|
|
Drywall/lumber/trim order & deliver |
|
|
Cabinets/Plumbing Fixtures order |
|
|
| T & M 9/14 |
Bathroom Expansion Drywall |
|
|
Framing 1- Furring and plumbing |
|
|
Kitchen Floor refinishing – since we have to let the floors dry, and won’t be able to do work, may be good while we wait for a permit |
|
|
Porch Demo |
|
|
| approx. 4 wks away |
Permit Approval |
|
| Weekend A (9/18-9/21) |
Sunroom Roof/Wall Demo/Windows |
|
|
Porch Footings |
|
|
|
Bath shower wall/bath floor/Sunroom Floor demo |
|
|
Plumbing Rough |
|
|
Electrical Rough |
|
|
Rough Inspection |
|
|
|
|
| Weekend B |
Insulation |
|
|
Drywall/Kitchen-sunroom-bathroom |
|
|
Spackle, sand, and paint kitchen/sunroom/hall |
|
|
Cabinets |
|
|
|
Counter tops |
|
|
Kitchen/Bath Finish Plumbing |
|
|
|
Whole House Clean |
|
|
|
Tile Flooring |
|
|
Trim Work |
|
|
| Weekend C |
Porch |
|
|
| Late November |
Final inspection |
|
|
|
Exterior fixes |
|
|
Filling in stucco in old doors and windows |
|
|
painting |
|
|
|
Other updates |
|
|
Furnace |
|
|
Air conditioning |
|
|
new windows around house |